RESOURCES & INFRASTRUCTURE

Green Building Practices

 

RECOMMENDATIONS and ACTIVITIES

 

PERSON/GROUP RESPONSIBLE

 

COSTS

 

PROJECTED

TIMELINE

 

PROGRESS

 

Recommendation 1: (SLRP—Physical Plant)  To engage in renovations and new construction in accordance with needs, the Long Range Plan, and the philosophy of “green” construction.

 

Activity 1: Determine which buildings will be renovated and those, which will be demolished to make room for new construction.                                              

 

Activity 2: Determine maximum number of residential students and build plan in accordance with those numbers.

 

Activity 3: Explore the merging of Student Woodworking area with the Maintenance Shop – possible renovation/reconstruction of Paradise.

 

Activity 4: Renovate Bookstore as a Student Center and merge operations with Stardust Bookstore.

 

 

 

 

 

1. Plant

 

 

2.  Plant/Admissions/Dean of College/Board

 

 

3. Plant

 

 

4. Plant/Business Office

 

 

1. Post a list of projects and costs that includes a target date for completion of each item.

 

2.Plan will be developed by May 2005

 

3.  Plan in place by December 2005

 

4.  Planning started May 2005

 

 

1. Building priority list developed for NEASC review, Spring 2006.

Projects in red are potential student projects